Full disinfection of water mains to IW-CDS-5020-03 Section 4.10.5 — method statement, dosing, 24-hour contact period, de-chlorination, flushing, and ISO 17025 accredited water quality sampling.
Get a QuoteAll pipelines must be disinfected prior to connection to the Irish Water Network. We carry out the complete disinfection sequence to IW-CDS-5020-03 (Section 4.10.5), including preparation of a method statement with drawings submitted to the Irish Water field engineer for approval before commencing. Dosing is achieved using a calibrated dosing pump with sodium hypochlorite solution. Free chlorine levels are verified using a Palintest Lumiso chlorine photometer at the beginning and end of the contact period. Following disinfection, the Main is flushed, refilled with potable water, and left to stand for 24 hours before water quality samples are taken for analysis at an ISO 17025 accredited laboratory.


Based in Co. Laois, working nationwide. Call us or send a message and we'll come back to you promptly.